THE SCHOOL BOARD OF BROWARD COUNTY, FLORIDA
(Procurement Services Request
Form)
CONTRACTS develops RFQ for A/E Services
1. Confirm budget and scope
2. Revise and Update RFQ (RFQ for A/E Services for Projects over $500,000)
3. RFQ Review by:
a. Project Management
b. Legal
c. M/WBE
d. Capital Systems
e.
Risk Management
CONTRACTS issues advertisement and RFQ for Board Approval
1. Develop schedule
a.
CRC schedules meetings
a.b.
Confirm Bidding Calendar Post on Outlook Calendar
1. Invite:
1. Reception Clerk
2. CONTRACTS Clerk
3. Coordinator
4. Construction Purchasing Agent
5. Staff Attorney
b.c.
Verify business day due date – Tuesday,
Wednesday, Thursday
2. Prepare Board Agenda Item (Agenda Shell ARFQ) (Collaboration Forms)
a. Attach RFQ including advertisement for signature
b. Retain original in Agenda Item Suspense File until approved
CONTRACTS issues advertisement and RFQ to RECEPTION
1. Sign and forward for newspaper
2. Post on DemandStar
3. Email RFQ to DemandStar
RECEPTION issues advertisement to media
1. Sentinel and Herald
2. Plan Rooms
3. Other Media
RECEPTION prints RFQ
RECEPTION issues RFQ to respondents and posts planholders on DemandStar
CONTRACTS schedules and
facilitates NEGOTIATION PARAMETER COMMITTEE
1.
Confirm Schedule
2.
Prepare Parameter Form (NPC Form)
3.
Prepare Meeting Agenda and Sign-In form (NPC
Meeting)
4.
Prepare Meeting Notice
5.
Post Outlook Schedule
a.
Invite:
i.
Executive Director, Compliance and Contracts
ii.
Director, Purchasing
iii.
Director, Capital Planning
iv.
Director, Risk Management
v.
Coordinator, Design and Construction Contracts
vi.
Senior Project Manager
vii.
Project Manager
viii.
Director, Design and Support
b.
Reserve Meeting Room
RECEPTION receives and records RFIs from respondents
RECEPTION forwards RFIs to CONTRACTS
CONTRACTS responds to RFIs
and forwards to RECEPTION and DemandStar (RFQ RFI)
1.Post Addenda
on DemandStar
2.1.Email
Addenda to DemandStar
RECEPTION issues hardcopy RFI responses to respondents and DemandStar
1.
Post Addenda on DemandStar
2.
Email Addenda to DemandStar
RECEPTION receives RFQ responses
RECEPTION records receipt of responses on DemandStar
RECEPTION collates and boxes responses for distribution
CONTRACTS prepares transmittal memo and forwards to RECEPTION
1. Prepare memo from Director to CRC Members (CRC Trans Memo)
RECEPTION delivers RFQ responses to CRC Members
RECEPTION secures master RFQ response set in Archive
CONTRACTS schedules CRC Meeting(s)
1. Prepare Draft Schedule and Submit to CRC
2.1.CRC votes
to approve schedule
3.2.
Distribute schedule to:
a. Board and CRC Members (CRC Sched Memo) (CRC Sched)
b. Principals and Project Managers (CRC Prin Memo)
c. Website
d. Prepare Advertisement (CRC Mtg Ad)
i. Post in Herald and Sentinel one week in advance of meeting
e. Post on DemandStar
f. Post on Outlook Calendar
i. Invite:
1. Deputy Superintendent
2. Director of Compliance
3. Director, Support Services
4. Coordinator, Design and Construction Contracts
5. Staff Attorney
6. Senior Project Manager
7. Manager, Facilities Audits
8. Compliance Officer, M/WBE Office
9. Project Manager
10. Principal
ii. Reserve Meeting Rooms
CONTRACTS facilitates CRC Meeting(s)
1. Prepare Agenda
a. Individual Score Sheets (CRC Indiv Score)
b. Summary Score Sheets (CRC Summ Score)
i. Email to Coordinator
2. Submit agenda to CRC Chair for Approval
3. Coordinate room setup
a. Facilities Serviceperson setup furniture
b. Technology staff setup recording equipment
4. Facilitate meeting support
a. Handouts
b. Refreshments
1. Track presentation times
2. Record votes
a. Individual Score Sheets
b. Summary Score Sheets
c. Computer Aided Scoring Technology (CAST)
3. Record Minutes
a. Outline Subject Headings
b. Summary discussions
c. Motions, Seconds, Votes (Names and Vote Number)
4. Memo from Director to Superintendent Advising of Ranking (CRC Supt Memo)
a. Attach:
i. Meeting Minutes
ii. Summary Score Sheets
iii. Vote Summary Page
5.
Post Tabulation on scheduled date
CONTRACTS receives response from Superintendent
CONTRACTS issues letter and PSA Draft to finalist regarding negotiations
1. Prepare letter from Director to Consultant (Conslt Negot Notice)
a. Attach draft PSA (A-E Agreement)
CONTRACTS issues letters to
unsuccessful respondents advising no longer under consideration
1.Prepare
letter from Director to Consultants (Conslt Not Selected)
CONTRACTS receives PSA documents and reviews response from Consultant
CONTRACTS submits insurance documents to RISK MANAGEMENT
1. Prepare transmittal from Coordinator (Conslt Insur Trans)
a. Attach Collaboration Form
b. Attach PSA
c. Attach Certificate of Insurance
d. Attach Project Specific Quote (A/E Projects Only)
CONTRACTS issues PSA to MANAGEMENT AUDITS
1. Prepare transmittal from Coordinator (Conslt Audit Trans)
1. Collaboration Form
CONTRACTS receives approval from MANAGEMENT AUDITS
1. Collaboration Form
CONTRACTS schedules and facilitates NEGOTIATION
PARAMETER COMMITTEE
1.Confirm
Schedule
2.1.Prepare
Parameter Form (NPC Form)
3.1.Prepare
Meeting Agenda and Sign-In form (NPC Meeting)
4.1.Prepare
Meeting Notice
5.1.Post
Outlook Schedule
a.Invite:
i.Director of Compliance
ii.
i.Director, Purchasing
iii.
i.Director, Capital Planning
iv.
i.Director, Risk Management
v.
i.Coordinator, Design and
Construction Contracts
vi.
i.Senior Project Manager
vii.
i.Project Manager
b.a.Reserve
Meeting Room
CONTRACTS schedules and facilitates NEGOTIATIONS COMMITTEE
1. Confirm Schedule
2. Prepare Parameter Form (NP Form)
3. Prepare Meeting Agenda and Sign-In form (NP Meeting)
4. Prepare Meeting Notice
5. Post Outlook Schedule
a. Invite:
i.
Executive Director, of
Compliance and Contracts
ii.
i.Director, Purchasing
iii.
i.Director, Capital Planning
iv.
i.Compliance Officer, M/WBE
Office
v.
ii.
Coordinator, Design and Construction Contracts
vi.
iii.
Senior Project Manager
vii.
iv.
Project Manager
b. Reserve Meeting Room
CONTRACTS revises PSA and Transmits to Consultant for
Execution (Consult Exec Ltr)
1. Attach PSA and Four Copies of Signature Pages
CONTRACTS receives executed copies from Consultant
CONTRACTS acquires School Board Attorney Approval
1. Prepare Transmittal from Coordinator to Staff Attorney (Consult Atty Review)
CONTRACTS processes BOARD item “Approval of Agreement”
1. Prepare Agenda Item (Agenda Shell AOA) (Collaboration)
a. Attach PSA and Attachments
b. Attach Four Copies of Executed Signature Pages
c. Retain original in Agenda Item Suspense File until approved
CONTRACTS receives approved BOARD item “Approval of Agreement” and signatures
CONTRACTS assembles Four Copies PSA and distributes Original Executed Copy of PSA and ATP to CONSULTANT (Consult NTP)
1. Distribute by cc Original Executed Copy of PSA to RECEPTION
2. Distribute by cc Copy of PSA to PM and CAPITAL SYSTEMS
3. Distribute by cc Original Executed Copy of PSA to CONTRACTS file
4. Distribute Construction Front-End documents to PROJECT CONSULTANT by attachment (CD-ROM A/E PSA)
5. Distribute Design and Material Standards to PROJECT CONSULTANT by attachment (CD-ROM A/E PSA)
6. Post results on DemandStar
PM reviews project
consultant’s 50% design review documents divisions 0 & 1 with CONTRACTS and
project consultant.
CONTRACTS reviews as to form
and provides updated documents.
PM submits Procurement Request Form to CONTRACTS
1. Attach:
a. Bidding documents
b. Budget Document
i. PFA Form (PFA)
ii. CFR Form (If Applicable) (CFR)
iii. Requisition (If Applicable) (REQ)
c. Schedule (Proj Sched)
d. Document Approval Form (Facilities Plan Review)
CONTRACTS reviews bidding documents Division 0 and 1 (CFED)
CONTRACTS prepares Agenda Item “Authorization to Bid” (Agenda Shell ATB) (Collaboration)
1. Attach Two Copies of Advertisement Signature Pages (00101)
CONTRACTS schedules bid opening
d. Bid Opening Date
1. Confirm Bidding Calendar (Outlook) (DemandStar)
1. Verify business day due date – Tuesday, Wednesday, Thursday
2. Post on Outlook Calendar and invite (Outlook)
a. Staff Attorney
b.
Executive Director, of Compliance and Contracts
c. Coordinator
d. Senior Project Manager
e. Project Manager
f. RECEPTION Clerk
g. CONTRACTS Clerk
h. Construction Purchasing Agent
3. Reserve Meeting Room
4. Post on DemandStar
CONTRACTS submits bid advertisement to RECEPTION (00101)
1. Signed Approval to Bid Advertisement
RECEPTION issues advertisement to media (00101)
4.1.
Sentinel and Herald
5.2.
DemandStar
6.1.Plan Rooms
7.3.
Other Media
CONTRACTS develops bid tabulation form
RECEPTION Issues Bidding Documents
1. DemandStar
2. Plan Rooms
a. Log as planholders on DemandStar
3. Walk-Ins
a. Log as planholders on DemandStar
RECEPTION receives, issues RFI# and records RFIs from planholders (00220)
RECEPTION forwards RFIs to PM hardcopy and Optiview (00220)
PM reviews and responds
to RFIs
PM forwards RFI to project consultant via hardcopy, fax and/or email with direction as to response
PM signs and submits
addendum to RECEPTION and copy to CONTRACTS (00910)
CONTRACTS reviews Addenda “as to
form”
RECEPTION issues addendum (00910)
1. Post Addenda on DemandStar
2. Email Addenda to DemandStar and/or
3.
Forward to printer for distribution
CONTRACTS prepares Bid Tabulation Form (Bid Tab)
1. List Planholders listed on DemandStar
2. Confirm planholder list with RECEPTION
RECEPTION receives bids
1. Post bid reception on DemandStar
2. Cease reception of bids at deadline and stamp Bid Tab Form
RECEPTION provides bids and bid tabulation to CONTRACTS (Bid Tab)
CONTRACTS conducts bid opening
1. Prepared Bid Tabulation Form (Bid Tab)
a. Duplicates for Staff and visitors
2. Script for Introduction (Bid Script)
3. Bid Opening Procedure
a. CONTRACTS Clerk Opens Sealed Bid Envelope
b. Attorney Reviews Bid Form and Attachments (00410)
c. Coordinator, Director or Senior Manager Reads Bid Into the Record
d. Witnesses Sign Official Bid Tab Form
CONTRACTS/ATTORNEY/PM/CONSULTANT review bid documents after bid opening
1. ATTORNEY reviews bid documents for legal form
2. CONTRACTS reviews bids for administrative compliance
a. Surety on Treasury List
b. Validate Signature and Seals
c. Verify License with DPR and Public Entity Crime list with DMS
d. Verify Submittal Checklist
3. CONSULTANT and PM review documents for budget, alternates, addenda
M/WBE reviews documents submitted directly by bidders and advises CONTRACTS
ATTORNEY advises CONTRACTS regarding bid evaluation
PM/CONSULTANT advise CONTRACTS regarding bid evaluation and recommendation
M/WBE advises CONTRACTS regarding administrative compliance
CONTRACTS develops Bid Tab posting and posts at display and
reception (Bid Tab)
1. Revise Bid Tab to include witnesses
2. Revise Bid Tab to Include recommendation
3. Post by Deadline at Display Case
4. Provide Copy to Reception
CONTRACTS provides original bid documents to RECEPTION
1. RECEPTION immediately provides copy to CONTRACTS File
RECEPTION duplicates bid documents and forwards to PM
CONTRACTS prepares Board Item for Award of Contract (Agenda Shell AOC) (Collaboration)
1. Attach Bid Tab
CONTRACTS issues Notice of
Intent to Award to CONTRACTOR (00505)
CONTRACTS issues Notice of Award to CONTRACTOR upon Board Approval (00510)
CONTRACTS receives contract documents from CONTRACTOR
CONTRACTS reviews contract documents
CONTRACTS forwards selected contract documents to RISK MANAGEMENT
1. Prepare transmittal from Coordinator (Contr Insur Trans)
a. Attach Collaboration Form
b. Attach Article 42 (00700) (00510)
c. Attach Certificate of Insurance
CONTRACTS forwards contract documents to MANAGEMENT AUDITS
1. Prepare transmittal from Coordinator (Contr Audit Trans)
a. Attach Collaboration Form
b. Attach Bid Tab
c. Attach all original documents submitted by contractor EXCEPT 00520, 00600, and 00610 (Copies Only)
1. Collaboration Form
CONTRACTS receives approval from MANAGEMENT AUDITS
1.Collaboration
Form
CONTRACTS schedules closing (If Applicable)
1. PM/CONSULTANT/CONTRACTOR/CONTRACTS attend closing
CONTRACTS issues Notice to Proceed (00550)
1. Original Document Distribution
a. 00520, 00600, 00610
i. Contractor
ii. Surety
iii. Reception
iv. CONTRACTS File
2. Copies to Consultant
3. Copies to PM
4. Copies to CAPITAL SYSTEMS
PM schedules Pre-Construction Meeting
Templates and forms are named in (Document Name)
THE SCHOOL BOARD OF BROWARD COUNTY, FLORIDA
FACILITIES AND CONSTRUCTION MANAGEMENT DIVISION
CONTRACTS PM develops
ATP for DCP Services
CONTRACTS PM develops
RFP for D/B Services
PM submits RFP and DCP to CONTRACTS
CONTRACTS issues advertisement, RFP, and DCP for Board Approval
CONTRACTS issues advertisement, RFP, and DCP to RECEPTION
RECEPTION issues advertisement to media and schedules deadline
RECEPTION prints RFPissues DCP
to printer
RECEPTION issues RFP
to respondents and records transactionplanholders
from printer
RECEPTION receives and records RFIs from respondents
RECEPTION forwards RFIs to PM
PM issues RFIs to DCP
DCP responds to RFIs
PM submits addenda to
RECEPTION
RECEPTION issues addendum to
printer
RECEPTION receives RFP responses
RECEPTION records receipt of responses
RECEPTION collates and boxes responses for distribution
RECEPTION issues addendum
CONTRACTS prepares transmittal memo and forwards to RECEPTION
RECEPTION delivers RFP responses to CRC Members
RECEPTION secures master RFP response set
CONTRACTS schedules CRC Meeting(s)
CONTRACTS facilitates CRC Meeting(s)
CONTRACTS facilitates BOARD Meeting
BOARD awards Contract
PM CONTRACTS issues
Notice of Award to CONTRACTOR upon Board Approval
CONTRACTS issues letters to
unsuccessful respondents advising process completepost bid
tab
PM CONTRACTS receives
contract documents from CONTRACTOR
CONTRACTS reviews contract documents
CONTRACTSPM forwards
selected contract documents to RISK MANAGEMENT
CONTRACTSPM forwards
contract documents to MANAGEMENT AUDITS and CAPITAL SYSTEMS
CONTRACTSPM schedules
closing if necessary
PM/DESIGN-BUILDER/CONTRACTS attend closing
CONTRACTSPM issues
Notice to Proceed
PM schedules Pre-Construction Meeting
Templates and forms are named in (Document Name)
THE SCHOOL BOARD OF BROWARD COUNTY, FLORIDA
FACILITIES AND CONSTRUCTION MANAGEMENT DIVISION
PM assigns design to Design & Support or
consultant, if necessary.
PM develops scope, budget, and schedule:
Summary Scope, Plans and Specifications
Adopted District Facilities Work Program (ADFWP) or
Capital Funding Request (CFR) or Requisition
Schedule – ASAP or time specific or date specific
PM provides initial estimate of Fixed Limit of
Construction Cost (FLCC).
PM selects cost estimator method.
PM forwards Authorization To
Proceed (ATP) for Cost Estimator to CAPITAL SYSTEMS.
PM receives ATP from CAPITAL
SYSTEMS.
PM issues ATP to Cost
Estimator.
PM receives cost estimate
and confirms or revises budget or suspends project.
PM requests OECS RFP #,
forms and name of next contractor in rotation from CONTRACTS.
PM issues RFP to contractor
selected by CONTRACTS.
PM coordinates all aspects of RFP prior to issue of
NTP.
PM provides PSRF,
Educational Specifications, scope, budget documentation, schedule,
and cost estimate to
CONTRACTS requesting that NTP be issued:
Procurement Services Request Form (PSRF)
Summary Scope
Two Signed and Sealed Plans
and Specifications (For Contract Set and Contractor) and
one reproducible set without holes, binding etc.
DSS Approval Letter
ADFWP or CFR or Requisition
Schedule – ASAP or time specific or date specific
Consultant’s probable cost
of construction or PM estimate or Construction Cost Consultant estimate or SBBC
Estimator’s estimate
CONTRACTS reviews for
compliance.
PM provides Educational Specifications, bidding
documents, scope, budget, schedule and cost
estimate as necessary to CONTRACTS, or PM requests
next OECS contractor in rotation from
CONTRACTS (See Alternate Procedure above:
Procurement Services Request
Form (PSRF) with PM and Senior PM signatures
Summary Scope
Plans and Specifications
3 sets of bidding documents
(2 sets of which are signed and sealed and one
double-sided reproducible set
without holes, binding etc.)
Design and Support Services Department Approval
Letter
ADFWP or CFR or Requisition
Schedule – ASAP or time specific or date specific
Consultant’s probable cost of construction or PM
estimate or construction cost Consultant estimate or SBBC Estimator’s estimate
CONTRACTS reviews scope,
budget, schedule, quantities and bidding documents for
compliance.
CONTRACTS issues Request for
Proposal to next OECSC in rotation.
OECSC submits proposal to
CONTRACTS.
CONTRACTS reviews contractor’s
proposal for administrative compliance.
CONTRACTS provides
contractor’s proposal to PM.
PM determines whether
proposal needs to be reviewed by estimator, or PM reviews proposal
with Senior Project Manager.
PM issues recommendation to
CONTRACTS to request Staff Estimator or Construction Cost
Consultant.
CONTRACTS Staff Estimator or
Consultant reviews and verifies proposal for contractual
compliance and independent
cost estimate and submits findings to CONTRACTS.
CONTRACTS provides Estimator or Consultant findings
to PM.
PM recommends action to take on proposal.
PM submits recommendation in
writing to CONTRACTS by returning the completed Project Manager Instruction
Memo that was attached to the Contractor’s proposal:
Proceed
with OECS contract
Issue NTP
Bonding required or
requested
Builders Risk required or
requested
Discontinue project as OECS and issue as a hard bid
or roll into other project.
CONTRACTS reviews PM
recommendation for compliance.
CONTRACTS approves or
rejects OECS proposal and PM recommendation.
CONTRACTS proceeds with OECS NTP if approved by PM.
CONTRACTS coordinates NTP:
Acquires signatures of
Contractor, CONTRACTS, PM and PM Director
CONTRACTS requests bonds and
builder’s risk insurance if necessary.
CONTRACTS forwards selected
documents to RISK MANAGEMENT and School Board Attorney:
Certificate of Insurance
Builder’s Risk if applicable
Specifications
Bonds if applicable
Legal if applicable
CONTACTS issues NTP, with
all required signatures, and approved proposal to CAPITAL
SYSTEMS.
CAPITAL SYSTEMS issues
purchase order number to CONTRACTS.
CONTRACTS issues Notice to
Proceed to OECSC with a copy to PM.
PM schedules
Pre-Construction Meeting.
PM administers OECS
contract.
PM submits change-orders to
CONTRACTS.
CONTRACTS reviews
change-order proposal for administrative compliance.
CONTRACTS Estimator, Senior
Project Manager or Consultant reviews and approves change-order proposal for
contractual compliance.
CONTRACTS provides
recommendation to PM.
CONTRACTS issues
change-order to CAPITAL SYSTEMS.
CAPITAL SYSTEMS issues
revised purchase order number to CONTRACTS.
CONTRACTS issues revised
purchase order number to PM.
PM issues change-order approval to OECSC.
CONTRACTOR submits completed
Certificate For Payment form, for either partial or final
payment, to PM.
PM reviews, approves, signs,
and has PM Director sign Certificate For Payment.
PM submits Certificate For
Payment to CAPITAL SYSTEMS.
CAPITAL SYSTEMS processes
payment.
Payment check is issued to
CONTRACTOR.
PM requests Inspector of
Record (IOR) inspection.
PM issues Certificate of
Contract Completion to CONTRACTS with attachments:
Certificate of Contract Completion
Open-End Construction Services Minor Project Closeout Form
CONTRACTS reviews for
compliance and forwards final contract sum to CAPITAL SYSTEMS.
CAPITAL SYSTEMS closes
purchase order.
Authorization To Proceed (ATP): Authorization to proceed with project issued to the independent
cost estimator consultant.
Fixed Limit of Construction Cost (FLCC): The dollar amount budgeted for the construction of the project.
Inspector of Record (IOR): Inspector from SBBC responsible for confirming that project has
been constructed in compliance with specifications, codes, statutes etc.
Notice To Proceed (NTP: Notice to Contractor to begin construction.
Open-End Construction Services (OECS): Term contract utilized for procurement of minor projects, which
are those valued at less than $500,000.
Open-End Construction
Services Contractor (OECSC):
Contractor who has been awarded an Open-End Construction Services
Contract
Procurement Services Request Form (PSRF): Form utilized by Project Managers to request service from the
Contracts Section.
Project Manger (PM): SBBC staff member responsible for overseeing project on behalf of
SBBC.
Request For Proposal (RFP): Request to the Contractor for pricing of a project
The School Board of Broward County, Florida (SBBC)
Templates and forms are
named in Procedure – Open-End Construction Services Contracts
PM develops scope, budget, and schedule
PM assigns design to Design & Support or
consultant, if necessary
PM provides Educational Specifications scope,
budget, and schedule as necessary to CONTRACTS
CONTRACTS
verifies scope, budget, schedule and quantities
CONTRACTS
issues Request for Proposal to next OECSC in rotation
OECSC
issues proposal to CONTRACTS
CONTRACTS
reviews proposal for administrative compliance
CONTRACTS
estimator or consultant reviews proposal for contractual compliance
CONTRACTS
provides recommendation to PM
PM and
CONSULTANT review proposal and recommendation
PM
approves or rejects proposal and forwards to CONTRACTS
CONTRACTS
issues approved proposal to CAPITAL SYSTEMS
CAPITAL
SYSTEMS issues purchase order to CONTRACTS
CONTRACTS
issues Notice to Proceed to OECSC and PM
PM
schedules Pre-Construction Meeting
PM issues
Certificate of Contract Completion to CONTRACTS
PM submits
change-orders to CONTRACTS
CONTRACTS
reviews proposal for administrative compliance
CONTRACTS
estimator or consultant reviews proposal for contractual compliance
CONTRACTS
provides recommendation to PM
PM issues change-order
approval to OECSC
PM issues
Certificate of Contract Completion to CONTRACTS
CONTRACTS
records final contract/project sum and advises CAPITAL SYSTEMS
CAPITAL
SYSTEMS closes purchase order
Templates and forms are named in (Document Name)
THE SCHOOL BOARD OF BROWARD COUNTY, FLORIDA
FACILITIES AND CONSTRUCTION MANAGEMENT DIVISION
CONTRACTS prepares advertisement for receipt of applications (Document Name)
CONTRACTS prepares Agenda Item for Authorization to Advertise (Document Name)
CONTRACTS submits advertisement for publication
1. Sentinel
2. Herald
3. DemandStar
4. Plan Rooms
RECEPTION receives Contractor Pre-Qualification Applications
RECEPTION logs applications on database
CONTRACTS prepares transmittal to CPQRC (Document Name)
RECEPTION distributes applications to CPQRC
RECEPTION retains “Original” Contractor Pre-Qualification Applications
CONTRACTS schedules CPQRC Meeting
1. Verify Date
2. Reserve Room on Outlook Calendar
3. Invite and Confirm:
a. CPQRC Members
b. Director of Compliance
c. Coordinator, Design and Construction Contracts
d. Construction Purchasing Agent
e. Schedule Meeting on Outlook Calendar
4. Coordinate room setup
a. Facilities Serviceperson setup furniture
b. Technology staff setup recording equipment
5. Facilitate meeting support
a. Handouts
b. Refreshments
CONTRACTS facilitates CPQRC Meeting
1. Record Results
2. Outline Minutes
a. Motions, Seconds, Votes (Name, Votes For and Against)
CONTRACTS prepares Agenda Item (Document Name)
1. Attach Certification Listing Summary
2. Attach Summary Checklist
CONTRACTS receives Approved Board Item
CONTRACTS prepares Responses to Applicants
1. Certification Letter
a. Prepare and Attach Certificate
2. Not Certified Letter
CONTRACTS logs actions on database
CONTRACTS posts updated list on DemandStar
MIS FIS posts
updated list on Website
Templates and forms are named in (Document Name)